Company
SITIE is among the most active and skilled operators nationwide in the domestic and international Oil & Gas industry, with over 70 years operating successfully on the field.
Based on its remarkable expertise SITIE can cover a broad range of services in a reliable way, not to mention complying with the strictest quality and safety requirements and, not last, respecting the environment.
The combination of a long and successful experience in the management and execution of complex projects and its strategic position in the center of European industrial area allowed SITIE to succeed in the Oil&Gas sector.
With a professional workforce that is flexible, experienced, capable and committed to delivering projects safely and to the Highest Quality Standards, we provide leading edge technical solutions in order to continue achieving our excellent track record of exceeding client's requirements on projects.
The core business of SITIE is the electrical and instrumentation (E&I) installation. From the power distribution, to the instrumentation and control, communication and automation.
One of SITIE strong assets is the accurate estimation that protects the client from any unpleasant surprise during construction works.
Activity
In detail the activities of E&I installation can be summarized as follows:
- Supply of components/instrumentation
- Installation/assembly
- Start-up and delivery of the plant
- Operator's training
- Maintenance
The installation activities of the electrical and instrumentation plants, that range from underground cable laying, to the installation and wiring of DCS, are evolving towards a "turnkey" supply that includes also engineering, project management, material supply, plant start-up and Client's technicians training.
Services
Services and Capabilities:
- Engineering Studies
- Cost Estimates
- Project Management
- Procurement
- Installation, Management & Supervision
- Inspection & Validation
- Commissioning & Start Up
- Operation & Maintenance
Projects
Project |
Rotterdam Capacity Growth |
Client |
NESTE |
End user |
NESTE |
Site |
Neste Netherlands B.V. |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
90 |
Amount |
> 10.800.000 € |
Project |
Maboqueiro Platform |
Client |
Gruppo Antonini S.p.A. |
End user |
Azule Energy |
Site |
Gruppo Antonini |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
30 |
Amount |
> 1.000.000 € |
Project |
NESTE Site Development Project |
Client |
Impes Service / Technip |
End user |
NESTE |
Site |
Neste Netherlands B.V. |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
50 |
Amount |
> 2.230.000 € |
Project |
New HDG Line & Color Coating Line |
Client |
Danieli |
End user |
Arvedi |
Site |
Servola , Trieste |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
50 |
Amount |
> 1.350.000 € |
Project |
Genesis Biotech Expansion Project |
Client |
Wood |
End user |
Teva |
Site |
Teva Ulm Germany |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
150 |
Amount |
> 14.000.000 € |
Project |
New Platform Tolmount Deck |
Client |
Rosetti Marino S.p.A. |
End user |
Premier Oil |
Site |
Rosetti Marino Spa - Cantiere Piomboni |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
100 |
Amount |
> 2.000.000 € |
Project |
Porvoo Turnaround 2020 |
Client |
Neste Oil |
End user |
Neste Oil |
Site |
Porvoo, Finland |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
50 |
Amount |
> 500.000 € |
Project |
Revamping Hot Strip Mill Plant |
Client |
Danieli |
End user |
Tata Steel |
Site |
Ijmuiden, The Netherlands |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
60 |
Amount |
> 2.560.000 € |
Project |
New Logistic Site |
Client |
Solesi |
End user |
ENEL |
Activity |
Electrical And Instrumentation Installations
Automation, Telecom & Communication System
Cyber Security
|
Manpower Peak |
40 |
Amount |
> 1.400.000 € |
Project |
Yara Bamboo Project - SS1Q |
Client |
TECNICAS REUNIDAS |
End user |
YARA |
Site |
Porsgrunn, Norway |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
150 |
Amount |
> 5.500.000 € |
Project |
Urea Granulation 8 Project |
Client |
TECNIMONT |
End user |
YARA |
Site |
Sluiskil, The Netherland |
Activity |
Electrical And Instrumentation Installations
HVAC
|
Manpower Peak |
100 |
Amount |
> 10.000.000 € |
Project |
Yara Syra 4 Project |
Client |
CASALE |
End user |
YARA |
Site |
Koping, Sweden |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
250 |
Amount |
> 14.000.000 € |
Project |
EFRA Project |
Client |
KINETICS TECHNOLOGY |
End user |
LOTOS ASFALT |
Site |
Gdansk, Poland |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
260 |
Amount |
> 10.000.000 € |
Project |
New Chemical Plant EPDM-GP27 |
Client |
SAIPEM |
End user |
VERSALIS |
Site |
Ferrara, Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
100 |
Amount |
> 7.200.000 € |
Project |
New Platform "Clara NW" |
Client |
Navalmare |
End user |
ENI E&P |
Site |
Cantieri Navali La Spezia |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
110 |
Amount |
>1.100.000 € |
Project |
New Platform "Litchendjili" |
Client |
Navalmare |
End user |
ENI Congo |
Site |
Cantieri Navali La Spezia |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
110 |
Amount |
>3.900.000 |
Project |
Heavy Residue Process Complex |
Client |
TECHNIP ITALY S.p.A. |
End user |
LUKOIL |
Site |
Bourgas, Bulgaria |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
680 |
Amount |
> 17.500.000 € |
Project |
Hydrogen & Hydroconversion Plant |
Client |
Technip KTI |
End user |
Iplom S.p.A. |
Site |
Busalla (GE) |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
100 |
Amount |
3.500.000 € |
Project |
PTA 2/3 Expansion Project |
Client |
TECHNIP ITALY S.p.A. |
End user |
BP CHEMBEL NV |
Site |
Geel, Belgium |
Activity |
Electrical And Instrumentation Installations
Control Room
DCS
SIS
|
Manpower Peak |
60 |
Amount |
> 5.500.000 € |
Project |
C4 Isomerization Debottlenecking |
Client |
TECHINT |
End user |
LYONDELLBASELL |
Site |
Rotterdam, The Netherlands |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
120 |
Amount |
> 2.500.000 € |
Project |
New SR3 & TG1 Plant |
Client |
TECNIMONT KT |
End user |
NYNAS |
Site |
Nynashamn, Sweden |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
150 |
Amount |
> 5.500.000 € |
Project |
LNG Receiving Terminal |
Client |
TS LNG |
End user |
GATE |
Site |
Rotterdam, The Netherlands |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
290 |
Amount |
> 10.000.000 € |
Project |
New Gas Compression Station |
Client |
RENCO |
End user |
FLUXIS |
Site |
BERNEAU, WEELDE, ZELZATE (BELGIUM) |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
120 |
Amount |
> 5.500.000 € |
Project |
New Lng Terminal |
Client |
TS LNG |
End user |
Dunkerque LNG |
Site |
Dunkerque, France |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
400 |
Amount |
> 27.000.000 € |
Project |
New Lng Terminal |
Client |
JV SAIPEM - TECHINT - PBG |
End user |
POLSKIE LNG SA |
Site |
Swinoujscie - Poland |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
350 |
Amount |
> 15.500.000 € |
Project |
Energy from Waste Facilities |
Client |
CNIM |
End user |
CLUGSTON |
Site |
Oxford, UK |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
150 |
Amount |
> 4.500.000 € |
Project |
ELEFSIS Refinery Update Project |
Client |
TECNICAS REUNIDAS |
End user |
HELPE HELLENIC PETROLEUM |
Site |
Elefsina, Greece |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
300 |
Amount |
> 13.000.000 € |
Project |
New Gas Treatment Plant |
Client |
ENI S.p.A. |
End user |
ENI S.p.A. |
Site |
Capparuccia, Italy |
Activity |
Electrical And Instrumentation Installations
EPC Contracting
|
Manpower Peak |
80 |
Amount |
> 5.000.000 € |
Project |
HALFDAN BC - Accommodation Top Side |
Client |
ROSETTI MARINO S.p.A. |
End user |
MAERSK OLIE OG GAS AS |
Site |
Marina di Ravenna , Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
130 |
Amount |
> 3.500.000 € |
Project |
Tout Lui Faut Refinery Expansion |
Client |
SAIPEM S.p.A. |
End user |
STAATSOLIE |
Site |
Paramaribo, Suriname |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
500 |
Amount |
> 8.000.000 € |
Project |
Horizon Oil Sand Project |
Client |
TECHNIP ITALY S.p.A. |
End user |
CNRL - Canada Horizon Oil Sands Project Upgrading |
Site |
Alberta, Canada |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
600 |
Amount |
> 97.000.000 € |
Project |
Resource Recovery Plant Waste to Energy |
Client |
Foster Wheeler Italiana S.p.A. |
End user |
Lomellina Energia S.r.l. |
Site |
Parona (PV), Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
80 |
Amount |
> 2.000.000 € |
Project |
Power Plant |
Client |
Foster Wheeler Italiana S.p.A. |
End user |
Voghera Energia S.r.l. |
Site |
Torremenapace (PV), Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
100 |
Amount |
> 3.000.000 € |
Project |
Combined Heat and Power Plant 1.200 MW |
Client |
ENIPOWER S.p.A |
End user |
SNAMPROGETTI S.p.A. |
Site |
Ferrera Erbognone (PV), Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
200 |
Amount |
> 8.000.000 € |
Project |
Combined Heat and Power Plant 800 MW |
Client |
ENIPOWER S.p.A. |
End user |
SNAMPROGETTI S.p.A. |
Site |
Ferrara, Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
150 |
Amount |
> 6.000.000 € |
Project |
Combined Heat and Power Plant 800 MW |
Client |
ENIPOWER S.p.A. |
End user |
SNAMPROGETTI S.p.A. |
Site |
Mantova, Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
180 |
Amount |
> 6.000.000 € |
Project |
Combined Heat and Power Plant 800MW |
Client |
ENIPOWER S.p.A. |
End user |
SNAMPROGETTI S.p.A. |
Site |
Ravenna, Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
150 |
Amount |
> 5.500.000 € |
Project |
New Acoustic Alert System |
Client |
SNAM RETE GAS - STOGIT |
End user |
SNAM RETE GAS - STOGIT |
Site |
Brugherio, Settala, Minerbio, Sabbioncello, Fiume Trieste, Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
50 |
Amount |
> 2.500.000 € |
Project |
Gas Sorting Centre |
Client |
STREICHER |
End user |
SNAM RETE GAS |
Site |
Minerbio, (BO), Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
50 |
Amount |
> 1.000.000 € |
Project |
New Power Plant |
Client |
TECNICAS REUNIDAS |
End user |
NESTE-BOREALIS-VEOLIA |
Site |
Porvoo, Finland |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
100 |
Amount |
> 4.000.000 € |
Project |
TL3 MTBE BDH and KTO5 Instrument |
Client |
NESTE OIL |
End user |
NESTE OIL |
Site |
Porvoo, Finland |
Activity |
Instrument work for Turnaround 2018
|
Manpower Peak |
50 |
Amount |
> 1.000.000 € |
Project |
Polyethylene Plant PE-3 UNIT-ISBL |
Client |
TechnipFMC |
End user |
UNIPETROL |
Site |
Litvinov, Czech Republic |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
250 |
Amount |
> 11.500.000 € |
Project |
Ammonia 4 Project |
Client |
TechnipFMC |
End user |
DUSLO |
Site |
Šaľa/Nitra, Slovakia |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
110 |
Amount |
> 4.500.000 € |
Project |
New Oil Center Completion |
Client |
TECNIMONT |
End user |
TOTAL E&P |
Site |
Corleto Perticara (PZ), Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
50 |
Amount |
> 2.000.000 € |
Project |
Nuclear Power Plant Boards |
Client |
SIEMENS |
End user |
SLOVENSKÉ ELEKTRÁRNE |
Site |
Mochovce, Slovakia |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
10 |
Amount |
> 200.000 € |
Project |
New Bioplus Project 1000 MTPY PHA Plant |
Client |
BIO-ON |
End user |
BIO-ON |
Site |
Castel San Pietro (BO), Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
100 |
Amount |
> 3.000.000 € |
Project |
CMP Expansion Project |
Client |
Spin / Amec Foster Wheeler |
End user |
Spin |
Site |
Torviscosa (UD), Italy |
Activity |
Electrical And Instrumentation Installations
|
Manpower Peak |
50 |
Amount |
> 2.500.000 € |